Council officers propose removing the Sidmouth Street cycle lane and letting cyclists share the pavements. Councillors choose on Wednesday 25 November.

The two-way cycle track on Sidmouth Street could be removed altogether. Council officers have put forward a new plan that takes every cycle lane off the road and lets cyclists share the pavements instead.

Councillors on the Traffic Management Sub-Committee will choose between that plan and the one they backed in March. They meet at 6.30pm on Wednesday 25 November at the Civic Centre (meeting agenda).

Overview

Councillors decide on 25 November whether to keep a southbound-only cycle lane on Sidmouth Street, as agreed in March, or remove all on-road cycle lanes and make both pavements shared paths. Officers say only about 55 bike trips a day use the street. Only 13 people answered the October consultation, and 7 objected.

The two options

The March scheme, which went out to consultation in October, would:

  • replace the two-way cycle track with a southbound-only cycle lane
  • add a second northbound traffic lane at the London Road junction
  • give two right-turn lanes from London Road into Sidmouth Street
  • give two right-turn lanes from Sidmouth Street into Queens Road

The new alternative goes further. It would:

  • remove all on-road cycle facilities from Sidmouth Street
  • make the pavements on both sides shared paths for people walking and cycling, between South Street and London Road
  • add a crossing with a central refuge island just south of the South Street junction, for both pedestrians and cyclists
  • widen the traffic lanes and parking bays

Both details come from the officers’ report to the sub-committee (Sidmouth Street Cycle Lane, Consultation Results). If councillors pick the alternative, a new consultation would start straight away and come back to them in January 2027. Officers say that would not delay the scheme.

Why officers changed their minds

The council counted cyclists and pedestrians over three weekdays in April, from 7am to 7pm. On an average day the surveys found:

  • 27 cycle trips heading north
  • 28 cycle trips heading south
  • no more than 14 cyclists in the busiest hour, both directions together

The busiest single day saw 80 cycle trips. About a quarter of cyclists, 27% northbound and 28% southbound, already rode on the pavement rather than the cycle track. Officers call the demand “very low” against the levels usually used to justify dedicated cycle lanes.

Pedestrians far outnumber cyclists. The survey counted about 100 people an hour on the east pavement at peak times, and between 108 and 149 on the west side.

Officers also found problems with the March plan. Keeping the southbound lane squeezes each traffic lane to 3 metres. Northbound cyclists would lose their own lane. Every earlier design also removed the two pedestrian islands, which officers now say could leave people crossing a two-lane road with poor visibility.

The report admits the pavements fall short of the recommended width for shared paths. National guidance suggests 3 metres; most of Sidmouth Street’s pavements are 2.5 to 2.75 metres, narrowing to 2.44 metres just north of South Street. Officers argue that guidance allows short exceptions, and that 14 cyclists an hour will rarely meet a pedestrian.

What people said in the consultation

The statutory consultation ran from 1 to 22 October and drew 13 responses. Six supported the March scheme and seven objected.

The report says most objectors called it “a step backwards” for cycling, walking and wider sustainability. Several said links to other cycle routes were poor. Others worried about losing the pedestrian islands near South Street, especially for people with reduced mobility. A smaller number backed the change because the current layout causes queues. Reading Cycle Campaign sent separate feedback with ideas to offset the loss, which officers say they are reviewing.

The report also accepts that a shared pavement could affect older people, people with mobility needs and people with visual impairments.

What it means for you

If you cycle the route, the report says the existing and preferred cycle route in the area remains Watlington Street. Confident cyclists would still be able to ride north on the road, which runs downhill.

If you drive, both options add a second northbound lane at London Road. The council expects that to ease queues on Sidmouth Street and London Road, alongside the new London Road bus lane now being built.

The cycle track was put in during 2020 with emergency Active Travel Fund money. It was made permanent in September 2022.

Also on the agenda

The same meeting will also consider:

  • a petition about the width restriction on Norcot Road, near the Pottery Road roundabout
  • consultation results for the outer section of the A4 London Road bus lane
  • the Bath Road and Castle Hill active travel scheme, where officers recommend making the traffic order
  • a 20mph limit for the Amersham Road estate, which officers recommend bringing in as advertised
  • extra parking permits for Cranbury College, which now runs a school minibus

The meeting is open to the public and is webcast on the council’s democracy site.